AAI and DIACL Sign Operations and Maintenance Agreement for Dholera International Airport
The Airports Authority of India and Dholera International Airport Company Limited have signed an O&M agreement for the upcoming greenfield airport in Dholera, Gujarat. The agreement sets up an operational partnership ahead of the airport’s planned start.
The Airports Authority of India (AAI) has signed an O&M agreement with Dholera International Airport Company Limited (DIACL) for the upcoming greenfield airport in Dholera, Gujarat. The agreement was reported on November 3, 2026. It is being seen as an important step in preparing the airport for operations.
Anami Pandey, General Manager (JVC/PPP-II), signed the agreement on behalf of AAI. H.M. Chavda, Chief Operating Officer, signed on behalf of DIACL. The signing took place in the presence of Parveen Chaudhary, Managing Director of DIACL. Officials said the agreement creates an operational partnership between the two organisations for the Dholera airport project.
Some reports describe the agreement as an “Operations and Maintenance” agreement, while others call it an “Operation and Management” agreement. In both cases, it covers the framework for how the airport will be run and maintained once it becomes operational. Detailed terms, such as the exact scope of work, the duration of the agreement and any financial arrangements, have not been made public in the available reports.
AAI is a statutory body under the Ministry of Civil Aviation. It manages and operates airports and provides air navigation services across India. DIACL is the company responsible for developing Dholera International Airport. It is a joint venture of AAI, the Government of Gujarat and the National Industrial Corridor Development and Implementation Trust (NICDIT).
This is not the first agreement between the two organisations for the project. In May 2023, AAI signed an agreement with DIACL to provide Communication, Navigation and Surveillance and Air Traffic Management (CNS-ATM) facilities and services at the new airport. The latest O&M agreement adds to that earlier arrangement and covers the wider operational side of the airport.
The agreement comes at a time when the airport is in its final stage of development. During a site review on July 14, 2026, Union Civil Aviation Minister Rammohan Naidu Kinjarapu said around 80 per cent of the overall construction work had been completed. At that time, the runway, taxiway and air traffic control tower were reported as complete, and the passenger terminal building was about 75 per cent finished. The Minister had said the Ministry would work with the Directorate General of Civil Aviation (DGCA) to obtain the airport’s operating licence, with a target of starting operations by September or October 2026.
As of now, the DGCA aerodrome licence for the airport has not been publicly announced, and commercial flights have not started. No airline has published a schedule for Dholera so far. A revised date for the start of operations has also not been officially announced.
The airport’s planned facilities include a 25,000-square-metre passenger terminal with an annual capacity of 20 lakh passengers. A dedicated 2,500-square-metre cargo terminal is also being built to support the industrial ecosystem developing in the Dholera Special Investment Region (SIR).
The airport is connected by road through the Ahmedabad–Dholera Expressway, which was inaugurated on March 31, 2026. The Union Cabinet has also approved ₹20,667 crore for the Sarkhej–Dholera rail corridor. The Minister has said its station will be located next to the airport terminal.
With the O&M agreement in place, the remaining key milestones for the airport are completion of the passenger terminal, the DGCA aerodrome licence and the announcement of airline schedules. Each of these will require an official announcement before the airport’s commercial operations can be considered confirmed.