Dholera Airport Still Awaits DGCA Licence: Commercial Flight Operations Yet to Begin
Dholera International Airport has not yet received its DGCA aerodrome licence, months after the Centre’s September–October 2026 target. No official start date or airline schedule has been announced, and commercial flights have not begun.
Dholera International Airport is the greenfield airport being built in the Dholera Special Investment Region (SIR) in Gujarat. It has not yet received its aerodrome licence from the Directorate General of Civil Aviation (DGCA). As of mid-November 2026, no official notice of the licence or of any scheduled airline operations has been made public. This means commercial flights have not started at the airport, even though the Union Ministry of Civil Aviation had set a target of September–October 2026.
That target was announced during a site review on July 14, 2026. Union Civil Aviation Minister Rammohan Naidu Kinjarapu said at the time that around 80 per cent of the airport’s overall construction work was complete. Civil Aviation Secretary Samir Kumar Sinha, Airports Authority of India (AAI) Chairman Vipin Kumar, senior officials of the Gujarat government and representatives of the airport consortium joined him for the review.
At the time of that review, the runway, taxiway and air traffic control (ATC) tower were reported as fully complete. The passenger terminal building was about 75 per cent finished. The Minister directed contractors to finish all on-site work by September. He also said the Ministry would work with the DGCA to get the airport’s operating licence within the next three months, so that commercial operations could begin by September or October.
The DGCA licence is the key milestone, not the construction percentage. In India, an aerodrome licence is mandatory before an airport can handle scheduled commercial flights. A runway and control tower can be complete while the airport still cannot legally operate a single passenger flight. Licensing usually comes after the remaining construction is finished and after airside infrastructure, navigation and safety systems are checked. Airlines then need approved schedules before they can sell tickets for a new route. So far, no airline has publicly announced flights to or from Dholera.
The airport’s planned facilities include a 25,000-square-metre passenger terminal that can handle 20 lakh passengers a year. A separate 2,500-square-metre cargo terminal is being built to serve the industrial ecosystem developing in Dholera SIR. The project is being developed by Dholera International Airport Company Limited (DIACL). It is intended to serve passenger and cargo traffic and to work alongside Ahmedabad’s Sardar Vallabhbhai Patel International Airport, about 80 km away.
Road connectivity to the airport is already in place. Prime Minister Narendra Modi inaugurated the Ahmedabad–Dholera Expressway on March 31, 2026. The 109-km corridor runs from Sarkhej to Adhelai and passes the airport site. During the July review, the Minister also said the Union Cabinet had approved ₹20,667 crore for the Sarkhej–Dholera rail corridor. He added that its station would be located next to the airport terminal.
At the review, the Minister described the airport as part of the larger plan for Dholera as a manufacturing and industrial centre. He linked it with the region’s semiconductor cluster and other industrial projects coming up in the SIR. The cargo terminal in particular is meant to support movement of goods from industrial units in the region.
The Ministry of Civil Aviation, DGCA, AAI and DIACL have not officially announced a revised timeline for the licence or for the first commercial flight. Timelines for the project have shifted before, and earlier government estimates had pointed to different completion dates. Any opening date now circulating should be treated as unconfirmed until an authority announces it officially. Until then, Ahmedabad remains the nearest operational airport for travellers to Dholera SIR.
The next milestones to watch are completion of the passenger terminal, the DGCA aerodrome licence and the first airline schedule. Each of these will need a formal announcement before commercial operations at Dholera International Airport can be considered confirmed.